ORGANOTECHNIE – Power distribution

CONTEXT

Organotechnie entrusted Bossard with the renovation of the electrical distribution system at its production site in La Courneuve (93).

  • Bossard teams carried out HV and LV sizing calculation notes for the site.
  • Supply and installation of a new HV/LV 20kV 630kVA transformer and a LV 400/230V 250kVA transformer.
  • Manufacturing of a 1000 A low-voltage main LV Board in our workshops at Cholet.

Constraints :

  • Works in a restricted environment at La Courneuve site.
  • Management of plant shutdowns for power cuts and main LV board changeover.